Projects Uncooled doorframes
Furnace renovation: example of a 4 working days project

Furnace renovation: example of a 4 working days project
Furnace renovation in 4 working days

Removing the damaged lintel (left) and mounting of a new lintel girder (right)
Removing the damaged lintel (left) and mounting of a new lintel girder (right)

Arrival and mounting of a new furnace door frame
Arrival and mounting of a new furnace door frame

Mounting of fast exchangeable prefab lintel blocks and day 4: finished
Mounting of fast exchangeable prefab lintel blocks (mounting time per block 15 min.) and day 4: finished.
Uncooled furnace doorframes
Uncooled doorframes